CL&P Switching Into 'Full Restoration Mode'

The utility says it's making 'excellent progress,' but 320,000 customers are still without power.

 

CL&P says it has almost completed its damage assessments and has made substantial progress in clearing roads, which allows it to transition fully into "restoration mode" on Thursday.

William Quinlan, a utility vice president, said at a 4 p.m. briefing Wednesday that by Thursday morning he would have an estimate for when the vast majority of customers would get their power back.

"We continue to make excellent progress," Quinlan said, adding that the priority will be restoring critical facilities such as hospitals, police stations, fire stations and water treatment plants. About 500 such facilities still don't have power, he said.

In addition, Quinlan said, the company has firm commitments from 300 additional line workers and 250 additional tree workers and hopes to put them in the field tomorrow. That would bring the total number of out-of-state line workers — in addition to the 400 employed by CL&P — to 1380. The total number of called-in tree workers — in addition to about 300 in state who work regularly with CL&P — would go up to 888, he said.

Quinlan said the company had shifted its strategy from last year, when 800,000 customers lost power after a rare October snowstorm. It now considers clearing downed wires the highest priority.

"The reason we're focused on downed wires," he said, "is that they present a public health and safety risk."

Quinlan said there were a "substantial number of resources" in both the southwestern and southeastern corners of the state, where the most residents have lost power.

About 350,000 customers have had power restored since the storm began, but 320,000 customers were still in the dark on Wednesday afternoon.

RIGHTfromWrong October 31, 2012 at 10:08 PM
That's nice that they have extra workers…NOT ONE CL&P yellow truck has been seen in Georgetown all day!
Curious October 31, 2012 at 11:24 PM
I really wish someone could explain to me why for the last three storms AT&T was able to restore telephone (and Internet) service to homes in literally hours... using the same telephone poles, while CL & P takes a week? This is not a sarcastic question, but something I would seriously like to understand.
Leon Karvelis November 01, 2012 at 11:33 AM
Have yet to see a single CL&P truck or crew. Drove around area yesterday and people are bearing up in good spirits. Emergency workers in Redding, Weston and Easton working hard and long hours. But there is little evidence that utility performance has improved measurably over last year's storms, despite lots of talk about how "prepared" they were. Leon Karvelis

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something